A package is a container that holds all the jobs that you want to execute for a specific schedule.
Select New from the Packages menu on the NextGen® Background Business Processor Manager main toolbar.
The Package Properties window opens.
Enter a name for the package in the Packagename field.
Set a priority for the package in the Priority field.
Note: At this time, the priority settings are not used by NextGen® Background Business Processor. Leave the Priority setting value at 1.
Select one of the following action on Upon completion list when the package processing is completed.
Do not notify: No notification email sent to any recipients on package success or failure
Notify on completion: Notification email sent to recipients on completion, regardless of whether package processing succeeds or fails
Notify on failed or Completed with failures: Notification email sent to recipients when package processing has either failed or completed with failure of one or more jobs
Notify on success: Notification email sent to recipients only when package processing succeed
On Notification e-mail, enter the email address for the recipients of the email notification that is generated when the condition indicated in the Upon completion field is met.
Note: If you enter more than one recipient, use a comma to separate the email addresses.
On the Server tab, select one or more servers that you want to permit to run the package. The package will run on the first permitted server that picks it up.