To update multiple tasks as completed at the same time, do the following:

  1. From the Enterprise Worklog Manager select all the tasks to mark as complete.
  2. After selecting all the tasks, right-click and select Open.
    The Edit Task window appears.
  3. In the Status and Priority fields, select the appropriate status and priority. Check the check boxes above the drop-down lists.
  4. Check the Completion Dt check box and select the appropriate completion date.
  5. In the Completed By field, select your user name, and select the check box above it.
  6. Select OK.
    A confirmation message displays prompting you to confirm the completion of multiple tasks at once.
  7. Select Yes.
    A confirmation message of the task completions displays.