Override the Process Date
If you have security rights for the Batch Process Date Override function, the Process Date Override field appears in the Batch Maintenance window.
- From the main toolbar, select the Posting
icon.
- Select the applicable batch.
- Select New and then select Batch.
The Batch Maintenance window opens.
- All transactions attached to the batch have a process date displaying in the Process Date field in the Batch Maintenance window.
- If you leave the Process Date field blank, the process date is the current date.
- The following list of rules and conditions control how the Process Date Override function and the Process Date Override field are used:
- You cannot select a date greater than the current date.
- You can override the process date for any new charge added per line item.
- The Process Date Override is the date last entered per the encounter.
- Only users with the correct rights and permissions can change the process date.
- Users without security rights see only the Process Date Override field when they view a charge with a Process Date Override entered by a user with security rights. They cannot edit the date.
- The 24-hour rule applies to the Process Date Override. The 24-hour rule is based on the Create Date instead of the Process Date. The application compares the Create Date to the current date; if they are different, the 24-hour lock-down period applies to the charge. If the 24-hour rule applies to a charge, no edits or changes can be made to it.
- When you use auto adjustments and create or update a charge and override the process date, the process date for the auto adjustment matches the process date for the charge.
- When reversing a charge or voiding a charge, the adjustment and reversed charge the current process date is applied.