Contract Exceptions
- The Cont Adj Amt (Contract Adjustment Amount)
The values that display in the Cont Adj Amt (Contract Adjustment Amount) column are derived from a calculation generated by the application. To calculate the Cont Adj Amt, use the following equation:
Cont Allowed Amt (minus [–]) Reimbursement (equals [=]) Cont Adj Amt
For this example, the following Contract values are used:
Cont Allowed Amt: $55.00
Reimbursed: $49.50
Cont Adj Amt: $5.50
- The Act Adj Amt (Actual Adjustment Amount)
The values that display in the Act Adj Amt (Actual Adjustment Amount) column come from Adjustments field on the Charge Posting window where adjustments are automatically calculated by the application, based on the contract information.
The Act Adj Amt is calculated using the following equation:
Charge (minus [–]) Cont Allowed Amt (equals [=]) Act Adj Amt
From the example given, the Act Adj Amt for this service item would be calculated as follows:
Charge: $65.00
Cont Allowed Amt: $55.00
Act Adj Amt: $10.00
- The Diff Adj Amt (Difference in Adjustment Amount)
The values that display in the Diff Adj Amt (Difference in Adjustment Amount) column are derived from a calculation generated by the application. To calculate the Diff Adj Amt, use the following equation:
Act Adj Amount (plus [+]) Cont Adj Amt (equals [=]) Diff Adj Amt
From the example given, the Diff Adj Amt for this line item would be calculated as follows:
Act Adj Amt: –$10.00
Cont Adj Amt: $5.50
Diff Adj Amt: $4.50